Sunday 16 November 2014

Christmas Parking Suspension

Temporary Suspension of Parking Enforcement at Grand Union Place.

East Thames would like to inform all residents that CES Parking Enforcement Service will be suspended for a set time during the Christmas Holidays. Please note that the suspension only relates to the dates mentioned below and at all other times drivers should complete the visitor vouchers/permit according to the parking procedures.

Parking enforcement on White Tower Way, Candle Street and All Courtyards will be suspended from 07:00am on Tuesday 23rd December 2014 to 07:00am on Monday 5th January 2015.

Street by Street

The latest issue of Street by Street is now online. You can read it here.

Gate Installation Update & Parking Arrangements

Please find below the estimated schedule of works for the installation of the new gates at GUP. Please note these are estimated dates so can change depending on any snagging issues. Drivers please take note of the planned days when works are carried out at your block as this will affect access in and out of the underground car park.

Residents will be permitted to park their vehicles in the courtyard area and Candle Street on the effected day as quoted below; however you must display your official East Thames/Newlon/Gateway underground car park permits which have been provided to you by your respective landlord. Any other vehicles identified without a relevant permit will receive penalty charge notice. Please can we request that Drivers park sensibly by avoiding blocking the bin chambers and other vehicles. Drivers can move their cars back into the car park once works are completed (estimated 2 days work on each block).

The new gates to be fabricated and galvanised and will be completed within next 10 days. Casements are being fitted currently to each individual car park ramp and will be complete by week commencing 17th November.
  • 19th November: Gate 1 installation Mercer Court 2 days gate install and 2 days electrical
  • 21st November: Gate 2 installation Gray Court 2 days gate install and 2 days electrical
  • 25th November: Gate 3 installation Coalstore Court 2 days gate install and 2 days electrical
  • 28th November: Gate 4 installation Tramway Court 2 days gate install and 2 days electrical
  • 3rd December: Gate 5 installation Johnson Lock Court 2 days gate install and 2 days electrical
  • 8th December: Gate 6 installation Firewatch Court 2 days gate install and 2 days electrical
  • 11th December: Gate 7 installation Horsley Court 2 days gate install and 2 days electrical